Phone: (780) 983-3416 Email: ric@dwcltd.ca

DWC Oilfield Construction & Maintenance
HOME
ABOUT
SERVICES
  • PIPELINE CONSTRUCTION
  • FACILITIES CONSTRUCTION
  • MAINTENANCE
  • WELDING
  • CUSTOM FABRICATION
  • QC/QA
SAFETY
PROJECTS
CONTACTS
CAREERS
DWC Oilfield Construction & Maintenance
HOME
ABOUT
SERVICES
  • PIPELINE CONSTRUCTION
  • FACILITIES CONSTRUCTION
  • MAINTENANCE
  • WELDING
  • CUSTOM FABRICATION
  • QC/QA
SAFETY
PROJECTS
CONTACTS
CAREERS
More
  • HOME
  • ABOUT
  • SERVICES
    • PIPELINE CONSTRUCTION
    • FACILITIES CONSTRUCTION
    • MAINTENANCE
    • WELDING
    • CUSTOM FABRICATION
    • QC/QA
  • SAFETY
  • PROJECTS
  • CONTACTS
  • CAREERS
  • HOME
  • ABOUT
  • SERVICES
    • PIPELINE CONSTRUCTION
    • FACILITIES CONSTRUCTION
    • MAINTENANCE
    • WELDING
    • CUSTOM FABRICATION
    • QC/QA
  • SAFETY
  • PROJECTS
  • CONTACTS
  • CAREERS

PROJECTS

16"Line lowering

vALVE & RISER REPAIR

vALVE & RISER REPAIR

  Excavated 100 meters of  16” pipeline that was still full of product. It was alive! lowering it 1 meter to ensure that it once again met the line depth required. 




PROJECT PICTURES

vALVE & RISER REPAIR

vALVE & RISER REPAIR

vALVE & RISER REPAIR

Pre-built and tested risers at DWC facility. Excavated and removed old valve section. Added pile supports and new above ground riser with valves. Fabricated and installed landing and erected fence all to relocate valves above ground.


PROJECT PICTURES

Mechanical Piping

vALVE & RISER REPAIR

Mechanical Piping

Design a centralize instrument air system in plastic's factory. DWC prebuilt the piping spools, Relocated the air equipment and installed the piping system at the 30ft ceiling height. DWC fabricated all the required supports and secured the equipment to the concrete flooring. 

PROJECT PICTURES

VALVE REPLACEMENT

VALVE REPLACEMENT

Mechanical Piping

Replacement of a compromised valve. Excavated and exposed line. Cut out section to replace. Fit and welded new section. Applied Denso tape. Filled area and cleaned to its natural state. 


PROJECT PICTURES

containment tank

VALVE REPLACEMENT

containment tank

Pigging facility containment catch basin. Client required a containment basin that also had deflecting shields to help with containment. DWC designed and built a customized containment with the lid also acting as the side deflector shields. 

PROJECT PICTURES

RemedIation

VALVE REPLACEMENT

containment tank

Dammed existing creek to stop flow to perform work on site. Creek was reshaped and built with rock edging. This resolved the current erosion issues while also achieving a natural look.


PROJECT PICTURES

Contact us to find out more

CONTACT US

ADDITIONAL PROJECT PICTURES

At DWC we have completed many different projects for all types of customer. Click on the More Project Pictures Button to see some more great pictures!

MORE PROJECT PICTURES

Copyright © 2023 DWC Oilfield Construction & Maintenance - All Rights Reserved.

Powered by GoDaddy

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept